15 km average oil pipeline in Middle Volga

Project
The oil pipeline for the field on average the Volga region
Customer
Information is available on demand
Terms
September-October, 2016
Volume
15 006 m
Diameters
8" (Du of 200 mm)
Pressure and working temperatures
4 MPas, 65 °C
Work scope
Fiberglass (glass reinforced epoxy) pipes manufacture and delivery
Order completion (grease, keys, shaped products)
Supervision and training
Description
Fiberglass (glass reinforced epoxy) pipes were laid in the oil pipeline project, based on low thermal conductivity, long (more than 50 years) service life and absolute corrosion material resistance.
Installation savings and high pipeline assembly speed were calculated thanks to the threaded connection, abandonment of heavy equipment and welding work. As a result, according to the customer's calculations, finished fiberglass pipeline cost was not more expensive than steel equivalent cost.
SIE "Fiberglass Pipes Plant" advantages
Joint tests have been conducted on fiberglass plaster factory’s territory, which allowed the customer’s representatives to verify the fiberglass (glass reinforced epoxy) pipes reliability and their compliance with the declared characteristics.
The factory met the tight delivery time while shipping the entire volume within 45 calendar days.
Joint coordinated work installation speed was 1200 loading meter per day.
The pipeline has been successfully completed ahead of schedule.